December

2008

Planning is submitted to build a 30,000 tonnes per annum composting facility. Earthworm is born!

December

2011

We successfully raise the £2m to build the facility through an Enterprise Investment Scheme (EIS)

October

2012

The composting plant is completed – on time and on budget.

June

2014

We raise £3.34m in EIS funds for the launch of Earthworm Energy, our solar development business.

September

2016

We follow Earthworm Energy with Reliance Energy, our back-up power development business, raising £5m in EIS funds.

October

2016

The original Earthworm composting plant successfully exits at £1.15 per share.

December

2016

Brand new Earthworm SEIS and EIS funds are launched.

June

2017

Our total funds under management pass the £50m mark for the first time.

December

2017

Earthworm Energy, our solar development business, successfully exits at £1.30 per share.

February

2018

Reale Basil (part of the Earthworm SEIS Fund) submits plans to build the UK’s largest vertical herb and salad farm in Crowland, Lincolnshire.

July

2018

We are nominated for ‘Best SEIS Investment Manager’ in the Growth Investor Awards 2018.

September

2018

Earthworm partners with the charity, Solar Aid, which uses solar power to combat poverty and climate change in remote parts of Africa.

April

2019

Funds under management pass the £100m mark.

June

2019

Team expansion and move to new HQ at Milton Park, Abingdon.

November

2019

Our EIS Fund reaches £60.9m.